Rain and cold dampen CRC progress
Heavy and consistent rains combined with near freezing temperatures during the week of January 15, 2007 have totally shut down the soldier pile work for the CRC. The project has experienced rainfall almost every day since the project started on December 18, 2006.
Posted By Rice University at 3:34 PM in Category:Construction