Campus Notification: Winter Road Work Projects December 5 through 7

Monday, December 5, a multi-phased project roadway project is scheduled to begin

Beginning on December 5, a multi-phased project in multiple areas around campus will start. The schedule to begin areas four and five is identified on the map below.

Area 4: December 5 through 7 - The parking area along the east side of the road will be used for two-way traffic during construction.

Area 5: December 5 through 7 - The curb and gutter work will be completed before the road work in this area.

Due to the project, there will be limited access to the South Stadium Parking lot. It is recommended that parkers access this lot via Rice or Greenbriar Blvd. entrances while work is taking place. Following this work, asphalt road removal, base repair, and grading will be scheduled to ensure proper drainage to the existing stormwater drain.

If you have any questions or concerns, please contact Joe Buchanan at x6373 or (832) 347-0919.

Roadway work December 5